Project Details

Engineering Services Home Back to Project List
Planholders Bid Results
Project Number: 2008083
Project Name: Alley between Joseph Avenue and Nebraska Avenue from Morton Street to Perry Street
Construction Estimate: $60,482
Location: Alley between Joseph Avenue and Nebraska Avenue from Morton Street to Perry Street
Description: Alley paving by Local Improvement District (LID)
Status: Construction
Contractor: Shamrock Paving
Comments:  
Project Manager - Design Project Manager - Construction Information Last Updated 
John Gomez, 625-6700 Mike Cash, 625-7722 June 1, 2009
 
Estimated Project Schedule
Award Date Construction Start Date Substantially Completed Date
June 1, 2009 June 2009 July 2009