Project Details

Engineering Services Home Back to Project List
Planholders Bid Results
Project Number: 2008080
Project Name: Alley between 7th Avenue and 8th Avenue from Jefferson Street to Monroe Street
Construction Estimate: $75,000 to $100,000
Location: Alley between 7th Avenue and 8th Avenue from Jefferson Street to Monroe Street
Description: Alley paving by Local Improvement District (LID)
Status: Design
Contractor: To be determined
Comments:  
Project Manager - Design Project Manager - Construction Information Last Updated 
John Gomez, 625-6700 Construction Management, 625-7722 March 9, 2010
 
Estimated Project Schedule
Award Date Construction Start Date Substantially Completed Date
March 15, 2010 March 2010 April 2010