| Project Number: |
2007160 |
| Project Name: |
Buckeye - Grace Transmission
Main |
| Construction
Estimate: |
$4.0 to $4.5
Million |
| Location: |
Buckeye-Grace
Avenue from Ruby Street to Upriver Drive |
| Description: |
Construct
approximately 3.7 miles of 30-inch ductile iron pipe to replace the
existing 24-inch steel pipe |
| Status: |
Construction |
| Contractor: |
Halme
Construction |
| Comments: |
|
| Project Manager - Design |
Project Manager - Construction |
Information Last
Updated |
|
Dan
Buller, 625-6700 |
Mike
Cash, 625-7722 |
April 3, 2009 |
| |
| Estimated Project Schedule |
| Award Date |
Construction Start Date |
Substantially Completed Date |
| March
16, 2009 |
Spring
2009 |
Fall
2009 |
|