| Project Number: |
2007052 |
| Project Name: |
Miami Court from
Buckeye Avenue South to End of Cul-De-Sac |
| Construction
Estimate: |
$108,000 |
| Location: |
Miami Court from Buckeye Avenue South
to End of Cul-De-Sac |
| Description: |
Pave and install curb and
sidewalks. Partial funding provided by
Local Improvement District (LID)
Pave an existing gravel roads. 0.035 miles long. |
| Status: |
Design |
| Contractor: |
To be determined |
| Comments: |
|
| Project Manager - Design |
Project Manager - Construction |
Information Last
Updated |
|
John Gomez, 625-6700 |
Steve Sather, 625-7722 |
January 24, 2008 |
| |
| Estimated Project Schedule |
| Award Date |
Construction Start Date |
Substantially Completed Date |
| To be determined |
Summer 2008 |
Summer 2008 |
|