| Project Number: |
2007051 |
| Project Name: |
Belt Street from Nora
Avenue to Montgomery Avenue and Surrounding Residential Streets -
10-Year Street Bond |
| Construction
Estimate: |
$1.4 to $1.6 Million |
| Location: |
Belt-Nora/Montgomery; Buell-Hemlock/Montgomery;
Cannon-Nora/Montgomery; Hemlock-Shannon/Montgomery; Indiana-Hemlock/Ash;
Knox-Belt/Culdesac; Mansfield-Belt/Elm; Montgomery-Nettleton/Belt;
Nora-Hemlock/Ash; Shannon-Hemlock/Elm |
| Description: |
Curb to curb restoration
on some of these roads, grind and overlay on the others |
| Status: |
Design |
| Contractor: |
To be determined |
| Comments: |
|
| Project Manager - Design |
Project Manager - Construction |
Information Last
Updated |
|
Joel Graff, 625-7722 |
Bill Todd, 625-7722 |
March 23, 2008 |
| |
| Estimated Project Schedule |
| Award Date |
Construction Start Date |
Substantially Completed Date |
| To be determined |
Spring 2008 |
Summer 2008 |
|