| Project Number: |
2006147 |
| Project Name: |
28th Avenue, 27th
Avenue, 26th Avenue from Chestnut Street to Oak Street; Oak St from 28th
Ave to 26th Ave |
| Construction
Estimate: |
$935,000 |
| Location: |
28th Avenue, 27th Avenue, 26th Avenue
from Chestnut Street to Oak Street; Oak St from 28th Ave to 26th Ave |
| Description: |
Pave and install curb and
sidewalks. Partial funding provided by the 10-Year Street Bond and
Local Improvement District (LID).
A 6” water line will also be installed on 26th from Oak to 410’
west of Oak |
| Status: |
Design |
| Contractor: |
To be determined |
| Comments: |
|
| Project Manager - Design |
Project Manager - Construction |
Information Last
Updated |
|
John Gomez, 625-6700 |
Steve Sather, 625-7722 |
January 24, 2008 |
| |
| Estimated Project Schedule |
| Award Date |
Construction Start Date |
Substantially Completed Date |
| To be determined |
Spring 2008 |
Summer 2008 |
|