| Project Number: |
2006043 |
| Project Name: |
Wellesley Avenue at
Belt Street Protected Phasing, Upgrade Signal |
| Construction
Estimate: |
$450,000 - $500,000 |
| Location: |
Wellesley Avenue at Belt Street |
| Description: |
Upgrade of existing signals |
| Status: |
Construction |
| Contractor: |
Red Diamond Construction |
| Comments: |
|
| Project Manager - Design |
Project Manager - Construction |
Information Last
Updated |
|
Gerald Okihara, 625-6700 |
Mike Cash, 625-7722 |
March 11, 2009 |
| |
| Estimated Project Schedule |
| Award Date |
Construction Start Date |
Substantially Completed Date |
| March 9, 2009 |
Spring 2009 |
Early Summer 2009 |
|