| Project Number: |
2005051/2005038 |
| Project Name: |
Maple Street and Ash
Street from Broadway Avenue to Northwest Blvd. - 10-year Street Bond |
| Construction
Estimate: |
$5.2 million |
| Location: |
Maple Street and Ash Street from
Broadway Avenue to Northwest Blvd. |
| Description: |
Rehabilitate and restore 2.4 miles of road, full depth curb to curb.
Fiber optic cable will be installed. The intersections of Northwest Blvd. and
Boone Avenue will be restored with cement concrete. This project
also will
install cable inside existing ducts already in the street, and add new
conduit from Maple Street Bridge to Northwest Blvd. This cable will be
attached to signals and cameras. |
| Status: |
Construction |
| Contractor: |
Inland Asphalt Company |
| Comments: |
|
| Project Manager - Design |
Project Manager - Construction |
Information Last
Updated |
|
John Miller, 625-6700 |
Bill Todd, 625-6700 |
March 19, 2008 |
| |
| Estimated Project Schedule |
| Award Date |
Construction Start Date |
Substantially Completed Date |
| March 17, 2008 |
Spring 2008 |
Summer 2008 |
|