Project Details
| Bid Tabs | ||
| Project Number: | 2011075 | |
| Project Name: | Division Street from Euclid Avenue to the Y Adaptive Signal Control System | |
| Construction Estimate: | $698,000 | |
| Project Location: | Division Street from Euclid Avenue to the North Division Street Y | |
| Description: | The project will install an adaptive traffic signal system. The project is funded with Federal funds. | |
| Status: | Design | |
| Contractor: | To be determined | |
| Comments: | ||
| Project Manager – Design | Project Manager – Construction | |
| Engineering Services, 625-6700 | Construction Management, 625-7722 | |
| Estimated Project Schedule | ||
| Construction Start Date | Substantially Completed Date | |
| Spring, 2012 | Summer, 2012 | |
| Award Date | Information Last Updated | |
| To be determined | January 30, 2012 | |