Project Details
| Bid Tabs | ||
| Project Number: | 2009134 | |
| Project Name: | 8th Avenue and 9th Avenue Water Transmission Main from Division Street to Hatch Road | |
| Construction Estimate: | $1.1 Million | |
| Project Location: | 8th Avenue and 9th Avenue from Division Street to Hatch Road | |
| Description: | The project will install a new 24-inch and a new 36-inch line in 9th Avenue. from 9th Avenue and Pine Street tank to Cowley Street, and in Cowley Street to 8th Avenue, and a new 18-inch line in 8th Avenue from Cowley Street west to Division Street | |
| Status: | Design | |
| Contractor: | To be determined | |
| Comments: | ||
| Project Manager – Design | Project Manager – Construction | |
| Dan Buller, 625-6700 | Bill Todd, 625-7722 | |
| Estimated Project Schedule | ||
| Construction Start Date | Substantially Completed Date | |
| Summer 2012 | Fall 2012 | |
| Award Date | Information Last Updated | |
| To be determined | January 30, 2012 | |