Project Details
| Bid Tabs | ||
| Project Number: | 2009086 | |
| Project Name: | Combined Sewer Overflow Basins 38, 39 and 40 Control Facilities | |
| Construction Estimate: | $6.9 Million | |
| Project Location: | South Riverton Dr. from Magnolia to Regal streets | |
| Description: | The project will construct below ground concrete sewer/ stormwater storage basins and associated overflow and cleaning appurtenances in South Riverton Avenue between Magnolia Street and Regal Street; install a 24-inch sewer main in South Riverton Avenue between Magnolia Street and Altamont Street; install a 36-inch sewer main in South Riverton Avenue between Cook Street and Regal Street. The project is funded by the Wastewater Management Department. | |
| Status: | Construction | |
| Contractor: | Halme Construction, INc. | |
| Comments: | ||
| Project Manager – Design | Project Manager – Construction | |
| Dan Buller, 625-6700 | Bill Todd, 625-7722 | |
| Estimated Project Schedule | ||
| Construction Start Date | Substantially Completed Date | |
| Spring 2012 | Fall 2012 | |
| Award Date | Information Last Updated | |
| March 19, 2012 | April 10, 2012 | |