Project Details

 Bid Tabs
Project Number:  2008046
Project Name: Hazel’s Creek Drainage & Conservation Facility: 3rd Detention Pond
Construction Estimate: $456,000
Project Location: Regal Street and 44th Avenue
Description: This project will construct stormwater control devices, detention and filtration ponds, enhancements to an existing wetland, pedestrian paths, and additional maintenance access to these facilities. The project is funded by the Wastewater Department.
Status: Construction
Contractor: Murphy Brothers, Inc.
Comments:  
   
Project Manager – Design Project Manager – Construction
Dan Buller, 625-6700 Construction Management, 625-7722
 
Estimated Project Schedule
Construction Start Date Substantially Completed Date
April 2012 July 2012
   
Award Date Information Last Updated
November 7, 2011 November 11, 2011