Project Details

 Bid Tabs
Project Number:  2006243
Project Name: Division Street from Spokane River to North City Limits – Dynamic Message Sign Deployment
Construction Estimate: $1.5 Million
Project Location: Division Street from Spokane River to North City Limits
Description: The project will install intelligent transportation devices (closed circuit TV, traffic detection and communication infrastructure) along Division Street to provide traffic information to the Public.  The project is funded by Highway Safety Improvement funds.
Status: Design
Contractor: To be determined
Comments:  
   
Project Manager – Design Project Manager – Construction
Gerald Okihara, 625-6700 Construction Management, 625-7722
 
Estimated Project Schedule
Construction Start Date Substantially Completed Date
Spring, 2012 Summer, 2012
   
Award Date Information Last Updated
To be determined January 30, 2012