Project Details

 Bid Tabs
Project Number: 2004047
Project Name: Martin Luther King Junior Way (Riverside Drive) Extension – Phase 1
Construction Estimate: $3.8 Million
Project Location: Martin Luther King Junior Way – Riverside Avenue east of Division Street
Description: This project will extend Martin Luther King Junior Way (Riverside Avenue) east from Division Street. The project is Federally funded
Status: Construction
Contractor: Spokane Rock Products
Comments:  
   
Project Manager – Design Project Manager – Construction
Dan Buller, 625-6700  Mike Cash, 625-7722
 
Estimated Project Schedule
Construction Start Date Substantially Completed Date
Spring 2011 Summer 2011
   
Award Date Information Last Updated
January 10, 2101 March 28, 2011